Page 1 of 1

Market Street, Perth, Shared Path - Construction Works

Posted: Thu Nov 24, 2011 2:00 am
by rolandp
E-mail from Perth City Link:
From week commencing Monday 28 November, minor construction works will occur along the Market Street shared cycle and pedestrian path next to the Perth Arena site.
The works are to create a new construction site entrance for the Perth City Link Rail Alliance.

From mid-December, heavy vehicles will be entering and exiting via the new entrance, adding extra traffic to the area.

Additional signage is being installed, however we encourage pedestrians and cyclists to take extra care when passing through this area.

Re: Market Street, Perth, Shared Path - Construction Works

Posted: Sat Nov 24, 2012 12:25 pm
by rolandp
Something is build on the PSP exit onto Market St, and given that there are signs on the freeway indicating Market St is closed this week-end, come Monday morning there may be something extra:
Image

An attempt to get information from:
City of Perth
MRA
Perth Link
Main Roards
Department of Transport
failed on Friday, so it remains a mystery what is being installed.

Re: Market Street, Perth, Shared Path - Construction Works

Posted: Sun Feb 17, 2013 1:50 am
by dampier
This has been dug up, the path now stops a little sooner and does not line up with the PSP on the southern side. There is a bitumen ramp on the northern side so be careful.